The work outlined in this project includes but is not necessarily limited to the following:
- Removal of all existing rear and Juliet balconies down to the structure.
- Supply and installation of new materials per the Project Drawings.
- Removal and replacement of deteriorated sealant at all transition joints, flashings, and penetrations.
- Removal and reinstatement of rear and Juliet balcony sliding glass doors to facilitate the replacement of exterior weather seals.
- Excavation of approx. 4' of overburden above foundation walls below entrances to townhouses at the north side of the property.
- Installation of cold-applied waterproofing system with drainage board at the foundation wall.
- Urethane crack injection repairs at leaking cracks located on the walls of effected garages.